Gray-green home veranda with shuttered window, worn painted steps, brick approach and mature oak beside saw palmettos.

The Flaggers Near Black Banks Drive Were Step One in a Longer Rebuild

October 29, 2026

For three weeks in September and early October, getting in and out of Black Banks on a weekday meant a timing decision. From 9 a.m. to 4 p.m., Georgia Power crews worked along Sea Island Road near Black Banks Drive. The road sometimes dropped to one lane, and flaggers waved traffic through the work zone. The crews packed up on schedule around October 7, and Sea Island Road looks the same as it did in August.

The county's notice described that work as soil borings "needed to support Georgia Power's reconstruction of transmission lines and other future utility improvements." The borings were groundwork. The stretch of road between Black Banks and the Frederica Road intersection is where two long-running projects overlap. One is Georgia Power's plan to rebuild the power supply to St. Simons. The other is Glynn County's planned roundabout at Frederica and Sea Island roads. Neither has a construction start date, and both run through the same corridor of poles and lines.

What the crews were drilling for

Soil borings come before the main work. Engineers pull samples of the ground to learn what it can hold before they design foundations for new structures. Glynn County's September 14 notice is plain about the purpose: the reconstruction of transmission lines, plus future utility improvements. The notice also says Georgia Power required daytime work for safety reasons, and the 9-to-4 window was set to keep traffic impacts down.

A second notice came four days later. Georgia Power would install utility poles along Sea Island Road near Cinema Lane from September 23 through September 25, again 9 a.m. to 4 p.m., with one-lane traffic and flaggers. The Cinema Lane notice doesn't say whether those poles belong to the transmission rebuild or to separate distribution work. On the road, both jobs looked the same: a lane closed, a flagger, a short wait.

The line Georgia Power says it will replace

The bigger plan behind the borings showed up in The Brunswick News. Joshua Peacock, Georgia Power's external communications lead for Coastal Georgia, told the paper that upcoming Golden Isles projects include three things. The first is replacing the transmission line that runs to St. Simons Island. The second is replacing distribution lines and poles on the island that are sometimes more than 60 years old. The third is building in redundancy so power stays on for more customers.

The Brunswick News quoted Peacock directly about what that means on local roads:

"Over the next year, people will see a lot of Georgia Power projects happening."

The same article reports that some projects may affect traffic and that the company would work with local officials to keep that impact small. Peacock gave the tradeoff in his own words: "the reliability and the capacity will be far more enhanced." He also pointed to growth: Glynn County is growing quickly, and the local grid needs upgrades to keep up.

The company's reasoning goes back to Hurricane Helene in 2024. Coastal Georgia escaped the worst of that storm, but across the company it led to the replacement of 11,800 power poles, 1,500 miles of power lines and 5,800 transformers. "There are parts of the grid we just rebuilt from scratch," Peacock told The Brunswick News. The St. Simons work is meant to rebuild ahead of the next storm instead of after it.

How long this lasts depends on who's describing it. Peacock spoke of "the next year." WTOC's June 2026 report on Georgia Power's coastal upgrades gave a longer window: "over the next few years," several key projects will focus on replacing poles and lines serving barrier islands, including St. Simons and Tybee. The WTOC piece also shows how long a line rebuild takes elsewhere on the coast. In Savannah, Georgia Power upgraded 2.7 miles of high-voltage transmission line, the final phase of a project that started the year before, and replaced 32 aging poles from the 1970s with composite poles. In Jesup, the rebuild of 20 miles of line with all-new poles and conductor wire began last year and is slated to wrap up the following spring. Both projects are measured in seasons, not weeks.

A power line already runs through the roundabout drawings

This is where the roundabout comes in. Glynn County's project page for the Frederica Road and Sea Island Road roundabout lists a $6 million budget approved in FY2023, in June 2022. Southeastern Engineering, the firm behind the Kings Way and Frederica Road roundabout, is leading the design. The page says the project is in final design, and the remaining steps are utility coordination and property acquisition.

The utility coordination involves major lines. A 2025 relocation agreement between the county and Georgia Power covers the roundabout project, and its plan sheet labels an existing "BRUNSWICK - EAST BEACH 115KV" line along with Georgia Power transmission structures in the work area. That 2025 agreement capped payment at $800,000. Under its terms, Georgia Power had no obligation to start unless the county authorized the work and returned the agreement by September 30, 2025.

Then on June 4, 2026, the Glynn County Board of Commissioners approved a utility relocation agreement with Georgia Power for the same roundabout. That one came to $1,287,738, paid from the Multi-Year Capital Projects Fund. The attachment in the June 4 minutes is titled as a Georgia Power distribution agreement. That leaves two agreements on the record for one intersection: an earlier one whose drawings show transmission structures, and a 2026 one labeled for distribution. The public documents don't explain whether the second replaces the first, covers different equipment, or reflects a changed scope.

The county's roundabout page and its September borings notice never mention each other. Still, every pole line serving that end of the island passes through the Sea Island Road corridor. Any work on those lines, for the island rebuild or for the roundabout, shows up as a lane closure on the road Black Banks residents use to leave the neighborhood.

Why the order of work matters at this intersection

A roundabout can't be paved where poles still stand. That's why the county lists utility coordination as one of the last steps before construction, and why it has now signed off on relocation money. Meanwhile, Georgia Power has been studying the soil along the same road to design rebuilt transmission structures. Both projects need poles and lines in their final positions before anything permanent goes in.

The county has planned for traffic during the build. The roundabout's center is offset so new pavement can go down while traffic keeps moving on the existing lanes. The design also aims to limit the impact on trees. The traffic case behind the project comes from counts taken over July 4th weekend in 2021, which projected benefits through a design year of 2041. The design was sized for the island's busiest weekend.

What has a date, and what doesn't

Here's the public record in order:

  1. June 2022: The roundabout is approved for FY2023 with a $6 million budget.
  2. September 30, 2025: The authorization deadline in the 2025 Georgia Power relocation agreement for the roundabout, which capped payment at $800,000.
  3. June 4, 2026: Commissioners approve the $1,287,738 Georgia Power relocation agreement for the roundabout.
  4. September 16 to October 7, 2026: Georgia Power soil borings near Black Banks Drive to support the transmission line reconstruction.
  5. September 23 to 25, 2026: Georgia Power pole installation near Cinema Lane.

Still unscheduled or unanswered in the public record:

  • No construction start or completion date has been published for the roundabout. The county page still lists utility coordination and property acquisition as unfinished.
  • Georgia Power hasn't published a route, schedule, or construction phases for the St. Simons transmission line replacement. Its public transmission projects page doesn't list Glynn County.
  • No public document says whether the rebuilt line will cross the marsh in the same place, go underground anywhere along Sea Island Road, or require tree trimming along the corridor.
  • The final route for the roundabout's planned multiuse pathway is still being worked out where it runs into trees.

Where the next notice will appear

So far, each piece of this work was announced on Glynn County's news page days ahead of time. The borings notice went up two days before crews started, and the Cinema Lane notice five days before. The county's news listing for October shows no new utility notice for Sea Island Road since the borings ended. It shows other items, such as tree maintenance at the Mallery ballfield. Georgia Power directs the public to GeorgiaPower.com/TransmissionProjects for updates on ongoing projects, according to The Brunswick News.

There's also a quick way to weigh in on county priorities before Friday. The 2026 Glynn County Community Survey asks residents about county services and quality of life, and it closes Friday, October 30. For anyone who spent September behind a flagger near Black Banks Drive, it's a timely place to say how construction traffic on Sea Island Road should be handled.

At the Angela Harrison Team | Frederica Realty, we follow the projects that shape daily life on this end of the island, from the poles along Sea Island Road to the roundabout plans at Frederica Road. If you'd like to talk through what this work means for your home in Black Banks, or for a property you're considering nearby, we're glad to share what we're seeing.